❮ Back

08381 | Bridge Replacement, Future Projects (Various)

This program provides funding for future projects related to bridge rehabilitations and replacements, statewide.

Limits: Bridge Replacement, Future Projects
Air Quality Code: S19

FY2024 TIP for NJ Program Years (in Millions)

PhaseFundFY24FY25FY26FY27LFY28-33
ConstructionNHPP$6.754$13.770$34.212$15.281$105.811
ConstructionBFP-OS-BRDG$30.618$17.918$20.768$27.418$0
ConstructionSTBGP-OS-BRDG$30.961$32.180$33.424$34.692$236.250
ConstructionSTATE$1.000$1.000$1.000$1.000$6.000
ConstructionHIP-BRR$13.275$13.275$0$0$0
Program Year Totals:$82.608$78.143$89.404$78.391
Total FY24-FY27 Cost:$328.546Total FY24-FY33 Cost:$676.607 
All costs in millions.

No milestones are available for this project.