DR1802 | Subway Structures Renovation (Various)

This program will provide for preventive repairs of pedestrian bridges, tunnels, subway stations, pump rooms owned by PATCO including but not limited to miscellaneous steel repair, concrete repair, joint filler, painting, waterproofing, and tunnel leakage mitigation throughout the PATCO High Speed Line System.

Limits: PATCO High Speed Line System
Air Quality Code: M8

FY2026 Draft TIP for NJ Program Years (in Millions)

PhaseFundFY26FY27FY28FY29LFY30-35
ConstructionSECT 5337$0$13.520$2.480$1.100$0
ConstructionDRPA$0$3.380$0.620$0.275$0
Program Year Totals:$0$16.900$3.100$1.375
Total FY26-FY29 Cost:$21.375Total FY26-FY35 Cost:$21.375 
All costs in millions.

No milestones are available for this project.