17357 | Bridge Maintenance Fender Replacement (Various)

This is an ongoing program to replace bridge fender and pier protection system elements that are in poor and critical condition. Fender systems and waterways are regulated by the U.S. Coast Guard and are required to be maintained in good working condition by the Code of Federal Regulations.

Limits: Bridge Maintenance Fender Replacement
Air Quality Code: S19

FY2026 Draft TIP for NJ Program Years (in Millions)

PhaseFundFY26FY27FY28FY29LFY30-35
ConstructionNHPP$4.000$15.000$4.000$15.000$57.000
ConstructionSTBGP-FLEX$1.000$5.000$1.000$5.000$18.000
Program Year Totals:$5.000$20.000$5.000$20.000
Total FY26-FY29 Cost:$50.000Total FY26-FY35 Cost:$125.000 
All costs in millions.