❮ Back

04324 |

This program provides funding for the betterment of existing highway lighting facilities when those facilities do not comply with current electrical codes and/or replacement equipment is not available. Due to high traffic volumes, maintenance of these existing facilities is hazardous to NJDOT personnel. The use of high-mast lighting will be investigated. ROW acquisition may be required.

Limits: Electrical Load Center Replacement, Statewide

FFY2026 TIP for NJ (FFY26-FFY29) Program Years (in Millions)

PhaseFundFY26FY27FY28FY29LFY30-35
ConstructionSTATE$4.000$4.500$4.500$4.500$30.500
Program Year Totals:
Total FY26-FY29 Cost:Total FY26-FY35 Cost: 
All costs in millions.

No milestones are available for this project.