D2023 | (Mercer County)
The project includes road diets and intersection channelization in the vicinity of the Trenton Transportation Center to improve mobility for bicyclists and pedestrians. The project will realign US-1 on-ramps and close the Chestnut Avenue Bridge to vehicular traffic.
Limits: Trenton Transit Center Circulation Improvements
| Phase | Fund | FY26 | FY27 | FY28 | FY29 | LFY30-35 |
|---|---|---|---|---|---|---|
| Construction | STBGP-TRENTON | $0 | $0 | $0 | $5.886 | $0 |
| Design | STBGP-TRENTON | $0 | $0 | $0.600 | $0 | $0 |
| Program Year Totals: | ||||||
| Total FY26-FY29 Cost: | Total FY26-FY35 Cost: | |||||
| All costs in millions. | ||||||