18378 | Route 130 SB, Bridge over Assiscunk Creek (Burlington City, Burlington County)
Initiated from the Bridge Management System, this project will replace or rehabilitate the structurally deficient bridge.
Limits: Bridge over Assiscunk Creek
Air Quality Code: S19
Phase | Fund | FY26 | FY27 | FY28 | FY29 | LFY30-35 |
---|---|---|---|---|---|---|
Preliminary Engineering | NHPP | $2.900 | $0 | $0 | $0 | $0 |
Design | NHPP | $0 | $0 | $0 | $0 | $2.900 |
Right of Way | NHPP | $0 | $0 | $0 | $0 | $0.380 |
Construction | NHPP | $0 | $0 | $0 | $0 | $20.280 |
Program Year Totals: | $2.900 | $0 | $0 | $0 | ||
Total FY26-FY29 Cost: | $2.900 | Total FY26-FY35 Cost: | $26.460 | |||
All costs in millions. |
Phase | Milestone | Estimated Date |
---|---|---|
Concept Development Initiated | 2019-07-03 | 2019-07-03 |
Develop Community Profile | 2020-09-07 | 2020-09-14 |
Purpose & Need Statement Completed | 2020-10-29 | 2020-10-29 |
Develop Alternatives | 2021-03-11 | 2021-04-08 |
Hold Public Information Center | 2022-01-31 | 2022-04-22 |
Authorize PE Funding | 2022-10-11 | 2022-10-17 |
Concept Development Completed | 2022-10-25 | 2022-10-25 |