18353 | Route 295, Sloan Avenue (CR 649) to CR 583 (Princeton Pike) (Lawrence Twp & Hamilton Twp, Mercer County)
Initiated by the Congestion Management System, this project will address capacity and operational improvements within the project limits. This project is planned to follow the Design Build delivery process.
Limits: Sloan Avenue (CR 649) to CR 583 (Princeton Pike)
Air Quality Code: 2040M
Phase | Fund | FY26 | FY27 | FY28 | FY29 | LFY30-35 |
---|---|---|---|---|---|---|
Preliminary Engineering | CMAQ | $7.000 | $0 | $0 | $0 | $0 |
Right of Way | CMAQ | $0 | $3.000 | $0 | $0 | $0 |
Construction | CMAQ | $0 | $0 | $0 | $29.000 | $27.000 |
Program Year Totals: | $7.000 | $3.000 | $0 | $29.000 | ||
Total FY26-FY29 Cost: | $39.000 | Total FY26-FY35 Cost: | $66.000 | |||
All costs in millions. |
Phase | Milestone | Estimated Date |
---|---|---|
Concept Development Initiated | 2018-05-14 | 2018-05-14 |
Purpose & Need Statement Completed | 2019-09-16 | 2019-09-16 |
Develop Alternatives | 2020-09-28 | 2021-03-30 |
Conduct Proposed Traffic Analysis | 2022-04-11 | 2022-07-27 |
Hold Public Information Center | 2023-01-24 | 2023-03-03 |
Authorize PE Funding | 2023-11-03 | 2023-11-13 |
Concept Development Completed | 2023-11-28 | 2023-11-28 |