This is an ongoing program to replace bridge fender and pier protection system elements that are in poor and critical condition. Fender systems and waterways are regulated by the U.S. Coast Guard and are required to be maintained in good working condition by the Code of Federal Regulations.

Limits: Bridge Maintenance Fender Replacement

FFY2026 TIP for NJ (FFY26-FFY29) Program Years (in Millions)

PhaseFundFY26FY27FY28FY29LFY30-35
ConstructionSTBGP-FLEX$1.000$5.000$1.000$5.000$8.140
ConstructionNHPP$4.000$15.000$4.000$15.000$26.260
Program Year Totals:
Total FY26-FY29 Cost:Total FY26-FY35 Cost: 
All costs in millions.