15321 | (Burlington County)
Initiated by the Bridge Management System, this project will replace the bridge, built in 1931.
Limits: Bridge over Mount Misery Brook
| Phase | Fund | FY26 | FY27 | FY28 | FY29 | LFY30-35 |
|---|---|---|---|---|---|---|
| Construction | NHPP | $0 | $12.950 | $0 | $0 | $0 |
| Right of Way | BFP | $0.200 | $0 | $0 | $0 | $0 |
| Program Year Totals: | ||||||
| Total FY26-FY29 Cost: | Total FY26-FY35 Cost: | |||||
| All costs in millions. | ||||||