15312 | (Mercer County)
Initiated by the Bridge Management System, this project will replace the structurally deficient bridge.
Limits: Bridge over Amtrak
| Phase | Fund | FY26 | FY27 | FY28 | FY29 | LFY30-35 |
|---|---|---|---|---|---|---|
| Design | STBGP-FLEX | $0 | $0 | $2.000 | $0 | $0 |
| Construction | STBGP-FLEX | $0 | $0 | $0 | $0 | $11.250 |
| Right of Way | STBGP-FLEX | $0 | $0 | $0.300 | $0 | $0 |
| Preliminary Engineering | STBGP-FLEX | $2.100 | $0 | $0 | $0 | $0 |
| Program Year Totals: | ||||||
| Total FY26-FY29 Cost: | Total FY26-FY35 Cost: | |||||
| All costs in millions. | ||||||