❮ Back

12307 | (Burlington County)

The purpose of this project is to reconfigure the Route 38 and South Church Street/Fellowship Rd. intersection layout, improve congestion, improve safety, and ensure ADA compliance throughout the intersection. In addition the existing S. Church St. Bridge will be replaced and widened, deficiencies in sidewalk, curbs and curb ramps will be addressed. The existing shoulders and auxiliary lanes will be brought into compliance with NJDOT standards.

Limits: (null)

FFY2026 TIP for NJ (FFY26-FFY29) Program Years (in Millions)

PhaseFundFY26FY27FY28FY29LFY30-35
ConstructionNHPP$0$32.400$0$0$0
UtilitiesNHPP$3.000$0$0$0$0
Program Year Totals:
Total FY26-FY29 Cost:Total FY26-FY35 Cost: 
All costs in millions.

No milestones are available for this project.