Action Item
Date Prepared: 02/12/2026Agenda Item:
5d Philmont Avenue/Tomlinson Road/Pine Road Improvements - 6 Point Intersection (MPMS #110315), Montgomery County – Federalize Project and add ROW Phase
Background/Analysis/Issues:
PennDOT has requested that DVRPC amend the FFY2025 TIP for Pennsylvania by adding the Right-of-Way (ROW) Phase to the Philmont Avenue/Tomlinson Road/Pine Road Improvements – 6 Point Intersection (MPMS #110315) project in the amount of $3,500,000 ($2,800,000 STU/$700,000 State 581) in FFY26.
A combination of conditions did not allow for the completion of the right-of-way (ROW) plan and encumbrance of the ROW funds on the previous TIP. Those factors included: • Drainage issues that have had extensive stormwater management review and re design of stormwater facilities
• Additional permanent acquisition related to the above stated drainage issues • PennDOT added scope in 2024 to include the Tomlinson Road grade crossing and Philmont Avenue/Byberry Road Intersection signal improvements • Permitting determination with modeling and DEP early coordination (also related to existing drainage issues at both culverts within the project limits)
A complete ROW plan has been prepared and the acquisition cost has been estimated by the District 6 ROW Unit. Because there are 24 claims, the District ROW Unit will be using an acquisition consultant.
This project proposes to streamline the six-legged intersection of
Philmont/Tomlinson/Pine Roads in two stages by removing both legs of Tomlinson Road from the intersection and relocating them. Additional shoulder and turning lane improvements along Philmont Avenue and Pine Road are also proposed.
The requested project ROW cost addition will be allocated to:
• ROW acquisition costs – $2,633,865
• Allowance for negotiation – $150,000
• Acquisition consultant & contingency – $716,135
Financial Constraint:
Financial constraint will be maintained by making adjustments to other existing TIP projects whose schedules or costs have changed. The attached fiscal constraint charts provided by PennDOT show all of the adjustments taking place in accordance with the TIP Memorandum of Understanding. All projects listed contribute to fiscal constraint.
Conformity Finding:
The TIP's current conformity finding will not be impacted by this amendment as this project is exempt from air quality analysis.
Cost and Source of Funds:
$3,500,000 ($2,800,000 STU/$700,000 State 581)
Recommendations:
Regional Technical Committee (RTC): Recommends Approval.
DVRPC Staff: Recommends Approval.
Action Proposed:
The DVRPC Board approves TIP Action PA25-082, PennDOT’s request that DVRPC amend the FFY2025 TIP for Pennsylvania by adding the Right-of-Way (ROW) Phase to the Philmont Avenue/Tomlinson Road/Pine Road Improvements – 6 Point Intersection (MPMS #110315) project in the amount of $3,500,000 ($2,800,000 STU/$700,000 State 581) in FFY26.